Tophat Factory

Client :

Tophat Industries Ltd

Location:

Derby, UK

Project:

Manufacturing Process Design and Installation

Timeline :

2017-2018

Value:

Confidential

Services:

Business Planning, Process Design, Offsite Consultancy

Project Description

Establishing a new manufacturing facility to supply Category 1 volumetric timber-framed houses and apartments for the UK residential market.

A comprehensive product portfolio had been developed by the client’s in-house architectural team to RIBA stage 2. Assessed as a viable product with sufficient vertically integrated demand, the business case was developed and approved for the fit-out of a 120,000 ft² manufacturing facility with a full production rate of 25 modules a week from a single shift operation.

Taking possession of a speculatively constructed distribution unit near Derby, the specification, selection, and installation of equipment took place over an 18-month period and included: - MEP fit-out, including a new higher-capacity incoming electrical supply - Extensive remodelling of the office and welfare facilities - Equipment installation - Human resource recruitment and training.

Description of our Work

APPLY provided a range of on-site and remote consulting services:

  • Equipment specification and sourcing

  • Factory - process development, in the form of 2d spacial layouts.

  • Workstation processes and Takt times.

  • Resource requirements.

  • Collaboration with the in-house architects, external design and structural engineer consultants, equipment, and systems suppliers.

  • Operational support to define and recruit the process engineering team and key production personnel.

  • Creating Standard Operating Procedures for all aspects of activity within the manufacturing environment.

  • Supporting installation, supply chain development and quality teams.